Laurens County Commission awards bids for almost $3 million in roadwork

The Laurens County Commission awarded bids Tuesday to two companies for an estimated $2.9 million in road resurfacing projects.

The commission voted last month to complete the list of almost 20 road projects ahead of schedule after the Georgia Department of Transportation made available $250 million to local governments for road repair, as part of the governor’s amended state budget. 

About $2 million came to Laurens County, and the county ponied up almost $1 million in local funding.

Stay in the know with our free newsletter

Receive stories from Laurens County straight to your inbox.

On Tuesday, the commission approved contractors for the projects, which were classified as either “non-subdivision roads” or “subdivision roads.”

Scruggs Co. was approved for non-subdivision road resurfacing, at $104.51 per pound of asphalt. That work is expected to be completed by August.

Sikes Brothers was awarded the bid for the shorter but more-expensive-to-resurface subdivision roads, at $140.53. Those projects were given a Nov. 1 deadline.

County Administrator Bryan Rogers noted the deadlines were shorter than most these days. The influx of state funding has more local governments bidding out projects, with them willing to give contractors more time to complete the work. 

“The problem we’re running into with all the state money out there right now …is that most people are putting 12-month time frames on any project,” said Rogers. “You get your best prices that way.”

The county’s request for proposals included prices and completion times.

The state funding and local match have been earmarked for the following projects: 

DISTRICT 1:

Pinehill Road

(U.S. 441 to Ga. 257)

3.12 miles

$390,000

Firetower Subdivision

1.20 miles

$126,000

Joy Lane Subdivision

1.00 miles

$ 90,300

Total – $606,300

DISTRICT 2:

David Mullis Road

2.85 miles

$356,000

Addie Trail

1.32 miles

$165,000

Daniel Estates

0.78 miles

$ 81,500

Greg Couey Road

0.25 miles

$ 26,250

Total – $628,750

DISTRICT 3:

Swinson Cemetery

(Paving Project)

0.50 miles

$112,000

Ed Swinson Road

0.85 miles

$106,125

Currie Road

0.73 miles

$ 91,250

Thomas Edmonds Road

0.30 miles

$ 31,000

Tanglewood East

1.30 miles

$162,500

Total – $502,875

DISTRICT 4:

Wayne Road

2.78 miles

$347,500

Evergreen (U.S, 441 To Old Toomsboro Road)

2.40 miles

$300,000

Total – $647,500

DISTRICT 5:

Fulgum Road

1.17 miles

$146,250

Master Moore Road

1.28 miles

$160,000

Arthur Graham Road

1.21 miles

$151,250

Edward Cox Road

0.57 miles

$59,850

Total –

$517,350

Total (All Projects) – $2,902,775

Author

Rodney writes about local politics, issues and trends, in addition to covering the Laurens County and Dublin City Schools beats and editing award-winning outdoors special section Porter’s Guide to Hunting and Fishing. The veteran newspaperman, with over three and a half decades of experience as a reporter and editor, has spent the bulk of his career covering various parts of Central Georgia in roles with The Courier Herald and Macon Telegraph.